|
Le
I usually have a project on somewhere, either working on my
own or with others.
If you would like to read about some of my projects, you
can find them on Adrian Pearce's British Mining Database
http://www.ap.pwp.blueyonder.co.uk/bmd.htm
However, if you want to be one of the first
to read about the "Big One", here it is;
Nenthead (North Pennines)
For the past few years I have been involved in a
project, of which one remarkable feature is the way that it has been kept
secret. Now, being virtually completed, it is time to reveal all.
If one enters the Caplecleugh High
Level, in the Upper Nent Valley, it is possible to explore this level for a
distance of about 500 metres to a solid collapse. There have been attempts to
dig through this fall in recent years, all unsuccessful. Many contemporary
researchers dismiss the Caplecleugh High Level as simply leading to Bog Shaft.
This could not be further from the truth.
If one could “spirit” oneself
through this fall, one would be able to pass other falls to eventually find
oneself in virtually solid passage driven mainly in the limestone. One would
then be able to proceed for about a mile, in a westerly direction, passing
through several recent digs to eventually reach the forehead about four hundred
meters from Longholehead Whimsy.
The level from the portal follows the
Cowslitts Cross Vein to its intersection with the Caplecleugh North Vein, this
is the area of the fall that blocks the level. The level then follows
Caplecleugh North Vein passing several branches on the left. These crosscut the
Caplecleugh Vein and Caplecleugh Sun Vein, one reaching the Caplecleugh Engine
Shaft. None of this area is shown on the abandonment plan, possible a factor
that has lead to confusion.
Proceeding westward one would pass
several sumps leading down to lower workings; these have concrete dams put in by
the Veille Montagne Company as this level was used as a spillway from the
compressors in Bog Shaft. Soon one would be in the area covered by the
abandonment plans, and reach a crosscut to Longcleeugh Vein going off on the
left. This level is blocked by collapses, but would have originally led to Bog
Shaft. Proceeding further to the west, one would pass Baisbecks Crosscut on the
left and further on the head of Archers Rise, which would be seen to be rigged
for SRT, this being the access point from the Caplecleugh Horse Level below. In
this vicinity is the name “Isaac Archer “ and “Priorsdale House Age 18
1850”. Further to the west a branch to the left follows Archers Vein, while
the main passage continues through a series of tight digs, and areas containing
gas and bad air, to end eventually at the forehead.
The last known people to enter these
workings, was a survey party including Thos F Walton, who is the signatory to
the abandonment plans. A curies fact is that this party all left their names on
the wall, and the date “February 23, 1926”. Yet the abandonment plans are
dated December 6th 1922.
There are also a few lines of what I
originally thought poetry
signed by an L. W. Pattinson. They are actually a few lines of a hymn from the Methodist
hymn book. (Info from Dave Carlisle, thanks Dave)
In darkest
shades if thou appear
My
dawning is begun
Thou
art my souls bright shining star
And
thou my rising sun.
L.W. Pattinson (a member of Thos Waltons survey
group) Feb 23 1926
The chalk survey marks are to be seen on the walls
going west as far as the Longlcleugh Vein crosscut; there was no sign that
anyone had been in the westerly extremity for any number of years.
Since the early 1990s I had been
exploring the Caplecleugh workings, and climbing the various rises. Later, I was
to team up with Ian Hebson, a fellow member of several northern mining
societies. Ian is a better climber than me, and together we have managed to
climb virtually every rise from the Caplecleugh Horse level into the Great
Limestone workings. Ian also gained Archers Rise and fitted it out with SRT
ropes, however at this point in time I am not prepared to describe the route in
detail because of safety considerations. Both Ian and myself have put a lot of
effort into this project, Ian’s climbing on several occasions put himself at
personal risk. I myself have spent up to ten and a half hours digging in there,
carrying materials including two Acro props through the working s and up the
various SRT rises.
Others, including Ians girlfriend
Kirsten Crowther, have been part of team on and off.
As I have stated in the forgoing
text, the main level from the collapse in the entrance section, to its forehead
in approximately one mile. If one includes the various side passages, stopes,
rises and sumps, there is probably about two miles of working not previously
accessed by modern explorers.
I would council a great deal of
caution to anyone considering attempting to locate the routes and explore these
workings. The routes itself is slightly unstable, and the western end of the
high level has gas and bad air. In sharp contrast the eastern end is very
strongly ventilated, in fact TOO strongly. It is the coldest place I have ever
visited underground, and therefore carries the attendant risk of someone going
into hypothermia.
It is my hope that this discovery
will prompt an organised effort to dig the collapse in the main level. This
would provide an easier access route for proper research, and greatly add to the
famous “Nenthead Through Trip”.
I am also in the process of
writing a book about Caplecleugh. This will include a diary of events relating
to the re accessing of the high level network, told as it happened. In the mean
time I welcome discussion with any contemporary researcher or historian who has
an interest in the area.
I
have to make a final comment. All this has only been achieved because I had the
freedom to this in my own way. Yes, this often meant going underground on my own
and working on my own, this is my way.
Frongoch
(Mid Wales)
Entry
to this mine involved a flat out crawl in running water up the partially choked
adit. This was impossible in wet weather, therefore for
some time I had been considering the adit shaft as another possible means of
entry. In 2002, with the mine being on the NAMHO meets list, I decided to do
something about it. Visiting the mine, accompanied by a friend from Welsh Mines
Society, we used an aluminum extending ladder to examine the shafts condition from below. To our
surprise, we found it possible to climb up to where daylight could be seen
coming in about thirty feet up. I have some doubt about it actually being a
shaft ever used for access; it’s actually the upper part of an open gunnis. It
was to prove quite interesting in itself, from part of the way down, old men's
workings can be seen extending towards the road. These workings are probably
quite old.
On
subsequent weeks, we commenced the work of clearing and stabilising the shaft
with the intention of fitting fixed wooden ladders. I had previously had talks
with the landowner, Mr. Arthur Edwards. I proposed that together with the other
work, the shaft would be capped with concrete and steel and fitted with a
manhole for access. Mr. Edwards readily agreed to this, however I was soon to
realise what a daunting task I had undertaken.
Our
initial work was stabilising the lower end of the shaft by fitting wooden
stemples backfilled with rock in places where there where unstable ledges. These
then provided useful staging for the fixed ladders. Next, a steep slope of earth
and rubble was stabilised by creating large “steps” using mine timber. Eventually,
much of this slope would be circumvented by the installation of fixed ladders. A
partial blockage of old car body sections was taken out and compressed into a
convenient cavity. This left the upper section of the shaft clear, a distance of
thirty feet from daylight to the rubble slope. It was decided to leave this for
the time being and concentrate on the surface work. One problem was that the
shaft collar was some fifteen feet down a steep grassy hollow. It was about ten
feet long by about 3 to 4 feet wide, following the direction of the vein away
from the road. It was only possible to descend on a rope, as the open shaft was
below. It was therefore decided to tackle the job in two halves, doing the road
side first. Concrete footings would be cast, and the shaft bridged by steel
reinforced concrete posts. Once this outside end was done, a way down could be
made to the platform created. This would make it easier to work. The shaft is
not vertical, but hades a few degrees, and the upper part of the hanging wall
was seen to be unstable. First task was to dig back from the collar to expose
the bedrock, this was done dangling on a rope. At the same
time, I had the opportunity to acquire some damaged concrete fence posts. These
are of cast concrete reinforced with very high tensile steel rods. A section of
rod about a foot long is impossible to bend by hand, although only about ¼ inch
thick. These, I considered ideal to form part of the capping, and they where
transported to the site. Initial work was stabilise the upper part of the
hanging wall, short 3 ft lengths of the concrete post were concreted in sloping
down at an angle into a convenient cavity. Other loose cavities were concreted
or bricked up. All done while hanging on a rope! Further stabilisation work done
at surface included filling various cavities up with liquid concrete as part of
building up a “collar” which would eventually be bridged over with the posts.
On Sunday 30th June I
returned to work solo in the shaft, installing a false floor at the random of an
“old mans level” heading towards the road. I suspect that there was one an
upper level from daylight, entering the gunnis at this point. I worked all day
at this, hammering into place heavy timbers to support the floor. More wooden
ladders where permanently installed in place, and an aluminium extending ladder
fitted from the false floor to surface. This latter item was temporary for the
NAMHO meet and will probably be removed at a later date. I don’t think it a
good idea to encourage casual access, although there is no intention to ever fit
a lock.
Later
work resulted in the whole shaft being capped. There is a large manhole cover
with a drain on either side. A length of scaffold pole has been concreted in
just below the drain on the footwall side. This is to provide a suitable belay
point in the event the first ladder is removed. The first pitch is 18 feet down
the footwall.
The
capping is actually in two halves, with the manhole and some concrete
lintels forming a "bridge" between the two halves. It was done this
way in order to avoid putting a load on an unstable area of the hanging wall.
The
reason for carrying out all this work is to secure the shaft against material
falling in from surface, with the attendant risk of the adit becoming blocked,
and to provide a more “sociable” method of entry. Up to the time of the work
on the shaft, the only method of entry was a flat out crawl in running water
from the adit portal..
|